Energy RFPs: Open Utility Solicitations and How They Work

Free 14-day trial. No credit card required.

This page lists open energy RFPs from more than 1,200 sources, including utilities, co-ops, municipal utilities, CCAs and state agencies. The list below updates daily. Below it is a practical guide to how utility procurement works: who issues solicitations, the main RFP types, and what evaluators look at when they score your bid.

Active Energy RFPs

Updated · 150 open

  1. distributed energy resources (der)CAISO · CA
    Due
  2. Wave Energy Feasibility Assessment – Additional Procurement DocumentsCaribbean Centre for Renewable Energy and Energy Efficiency
    renewable energy
  3. energy storageME
    Due
  4. renewable energyISO-NE · NH
    Due
  5. Request for Proposals: North Carolina State Energy Program Energy Efficiency SubgrantNorth Carolina Department of Environmental Quality (State Energy Office)
    energy efficiency building upgradesNC
    Due
  6. energyMN
  7. energy efficiencyOK
    Due
  8. renewable energy credits (recs)VA
    Due
  9. renewables + storageSC, NC, VA
  10. energy storageNY
    Due
  11. Energy Storage System Phase IIGuam Power Authority
    energy storageGU
    Due
  12. Second Long-Term (LT2) Request For Proposals - EnergyOntario Independent Electricity System Operator
    energy

+138 more open RFPs in this view, with documents, deadlines and alerts.

See all 150 RFPs free →

Aggregated by Energy Adepto from 1,200+ utility, ISO and agency sources.

What are energy RFPs?

An energy RFP (request for proposals) is a formal solicitation in which a utility, electric cooperative, municipal utility, community choice aggregator (CCA) or state agency asks for competitive bids. The buyer may want generation, storage, capacity, renewable energy certificates (RECs) or energy services. The RFP spells out what the buyer needs, the contract structures it will accept, how bids will be scored, and the schedule.

For developers, energy RFPs are one of the main ways utility-scale projects get contracted. In many states, competitive bidding is required. Oregon’s competitive bidding rules (OAR Chapter 860, Division 89) apply when a utility plans to acquire resources or contracts above 80 MW in aggregate and longer than five years. Washington requires all-source RFPs tied to the utility’s integrated resource plan (IRP). Other states take different approaches, but the pattern is similar: a resource plan identifies a need, and a solicitation fills it.

That matters for planning your pipeline. Most utility solicitations can be anticipated months ahead, so you don’t have to rely on spotting the RFP the week it posts.

Who issues energy RFPs

Utility RFPs come from several kinds of buyers. Each one behaves differently.

Issuer typeHow they tend to procure
Investor-owned utilities (IOUs)Large, formal and often commission-supervised solicitations tied to an IRP. They usually use an independent evaluator, with long timelines and detailed forms.
Electric co-ops and G&TsGeneration and transmission co-ops run sizable solicitations for their members. Formality varies, and some processes are run through consultants.
Municipal utilities and public powerSmaller, less frequent RFPs that are often governed by city procurement rules and council approval. Some joint action agencies buy on behalf of many cities.
Community choice aggregatorsFrequent solicitations driven by clean energy targets, often for PPAs and RECs. They can move faster than IOUs.
State agencies and authoritiesProgram-driven solicitations, such as NYSERDA’s in New York, often for RECs or specific technologies, on a published schedule.
Corporate and C&I buyersPrivate RFPs for virtual or physical PPAs and on-site projects. Usually run by advisors, with less public visibility.

Types of energy RFPs

The RFP type tells you a lot about how to position a bid.

All-source RFPs. These are technology-neutral solicitations open to any supply-side resource (and sometimes to demand-side resources). You compete against gas, storage and other renewables on cost and on the capacity value the utility’s model gives you. Effective load carrying capability (ELCC) or accredited capacity often decides the outcome as much as price does.

Renewable or technology-specific RFPs. These are solar, wind or storage solicitations, often driven by a renewable portfolio standard or a clean energy target. Competition is narrower, but so is the buyer’s tolerance for deviations from the spec.

Capacity RFPs. The buyer needs accredited capacity by a certain date, often to meet a resource adequacy requirement. Deliverability and in-service date matter more than energy price.

REC and environmental attribute RFPs. These ask for unbundled RECs or attributes only. They can suit operating projects or projects with merchant energy exposure.

PPA vs. build-transfer or asset acquisition (BTA/PSA). Many RFPs accept both. A PPA keeps you as owner-operator. Under a BTA, you develop and build the project, then the utility buys it at or near COD. These are two different business models, so price and risk-allocate them separately.

Energy efficiency and demand response. Some utilities procure load reduction through RFPs. These matter mostly to DER and efficiency vendors.

Distributed and community solar. These are smaller, distribution-connected projects, often under a state program. Interconnection is simpler, but program rules on subscribers, siting and pricing drive the bid.

How the utility RFP process works

The details vary by state and utility, but most commission-supervised utility solicitations follow the same arc.

  1. Resource need. The IRP or a commission order identifies a capacity or energy need, often with a preferred portfolio.
  2. Draft RFP and stakeholder comments. Many states require the draft to be filed for review. In Washington, interested parties get 45 days to comment on a filed RFP. Comments are a chance to push back on terms that would exclude your project type.
  3. Bidder conference. The utility or its administrator walks through the RFP and takes questions. Q&A logs are often posted afterward, and they are worth reading closely.
  4. Notice of intent and registration. Many RFPs require a notice of intent, an NDA or a registration step before proposal submission. This window is short and easy to miss.
  5. Proposal submission and bid fees. Many RFPs charge a bid fee per proposal or per variant. Submissions usually include a pricing workbook, technical forms, interconnection and site control evidence, and financial information.
  6. Independent evaluator review. In many states an independent evaluator (IE) monitors the process. Oregon requires utilities to engage an IE before issuing an RFP covered by its rules. Washington requires one when the utility or an affiliate is bidding, and the IE then scores and ranks bids alongside the utility (WAC 480-107-035).
  7. Quantitative (Price) and Qualitative (Risk) scoring. Price scoring usually means modeling each bid’s cost and value to the system, typically in the form of a Levelized Cost of Energy (LCOE) and Levelized Cost of Capacity (LCOC) calculation. Non-price scoring covers development maturity, interconnection status, site control, permitting, experience, credit and contract deviations.
  8. Shortlist. Top bids are shortlisted. Sometimes further analysis is done, like a nodal analysis with potential portfolios of shortlisted projects. In some states the commission reviews or acknowledges the final shortlist.
  9. Negotiation. Contract terms, security and price get finalized. Shortlisted projects can still drop out at this stage.
  10. Regulatory approval. Many contracts or acquisitions need commission approval before they are final.

Typical timelines. These ranges vary widely by state, utility and RFP size. Expect about three to six months from draft RFP to issuance, one to three months from issuance to proposal deadline, three to six months for evaluation and shortlisting, and several more months for negotiation and approval. From the first draft to an approved contract, a large IOU solicitation can take a year or more.

Where to find energy RFPs (and why it's hard)

There is no central registry for utility solicitations. Energy RFPs get posted on:

  • Utility procurement and “supplier” pages, often several clicks deep
  • PUC dockets, where draft RFPs, IE reports and approvals are filed
  • Websites of RFP administrators and independent evaluators
  • Trade press and industry association newsletters
  • Email distribution lists that only reach registered bidders

Formats vary from a press release to a 100-page PDF buried in a docket. The hardest part is timing: notice of intent windows can be just a few days after release, so a solicitation you find two weeks late may already be closed to you.

How Energy Adepto helps

Energy Adepto monitors 1,200+ sources daily, including utility sites, dockets, procurement platforms, administrator sites and industry lists. New energy RFPs are added as they’re found. You can filter by technology, ISO, state and issuer type, and set alerts so you hear about relevant solicitations when they post. Each listing links to the source documents, and the AI assistant summarizes long RFPs into the requirements, key dates and contacts you need to make a go/no-go call. That means your team spends less time searching and more time on bids worth pursuing.

Browse energy RFPs by technology, market and state

By technology

By market

  • ERCOT RFPs
  • MISO RFPs
  • SPP RFPs
  • PJM RFPs
  • CAISO RFPs

By state and issuer

  • Texas Utility RFPs
  • Electric Co-op RFPs

Related guides

FAQ

It depends on the issuer. Large IOUs typically run major solicitations every one to three years, tied to their IRP cycle. CCAs and state programs often follow an annual or published schedule. Across all issuers, new utility RFPs post every week, which is why the list above updates daily.

An RFI (request for information) gathers market information and usually doesn’t lead directly to a contract. An RFQ (request for qualifications) screens bidders on experience and capability, sometimes before an RFP. An RFP asks for priced, binding or indicative proposals that the buyer will evaluate and award.

Most utility-scale RFPs require at least an active queue position, and many score you higher for completed studies or an executed agreement. Some accept earlier-stage projects but discount them in non-price scoring. Check the eligibility section, because this threshold varies a lot.

An independent evaluator is a third party, independent of the utility and bidders, that oversees the solicitation for fairness. In some states it also scores bids and reports to the commission. IEs are especially common when the utility or an affiliate is bidding.

Commission-supervised solicitations are often visible months ahead through IRP filings and draft RFP dockets. Smaller utilities, co-ops and municipal utilities may post with little notice. Watching dockets and setting alerts gives you the most lead time.

Many utility RFPs charge a bid fee per proposal, and some charge per project. Fees and refund rules are set in each RFP, so check the submission section before you finalize how many options to submit.